Final chapter of the arch part II

November 8, 2019

Today we poured the concrete for the front of the arch, so part II. Now only the middle part needs to be done and the reconstruction of the arch is complete!
Some facts:
* 11 mixers of 300 liter of concrete
* 33 bags of cement
* 10 bags of vibres
* 16.5 liter of waterproofing stuff
* 7500 kg = total weight of the concrete
* 50 stamps to hold up the forms
* machines used: Merlot (crane), Wacker Neuson (excavator), Ahlmann (loader with mixer)
* 4 hours and the job was done !